On Wed, 2024-05-29 at 10:19 +0200, Jan Beulich wrote: > On 29.05.2024 10:03, Oleksii K. wrote: > > Hello everyone, > > > > I would like to announce that I have decided to update the Xen 4.19 > > schedule due to the extended feature freeze period and the upcoming > > Xen > > Summit next week. > > > > I propose the following updates: > > Code Freeze: from May 31 to June 7 > > This is almost fully the week of the summit. With ... > > > Hard Code Freeze: from June 21 to June 28 > > ... this, did you perhaps mean May 31 to June 20 there? > > > Final commits: from July 5 to July 12 > > Somewhat similarly, what's between June 28 and July 5? It should be RCx ( IIUC how it was done previously ) + bugfixes for serious bugs (including regressions), and probably low-risk fixes only Let me share the updated schedule as I made incorrect calculations: Code Freeze: Fri, June 14 (+2 weeks from Feature Freeze, considering the week of the summit) Hard Freeze: Fri, June 28 (+2 weeks from Code Freeze, usually it is +3 weeks, but I think we can go with +2 and extend ( to 3 weeks ) if necessary) Final Commits: Fri, July 12 (+2 weeks from Hard Freeze) Release: Wed, July 17 ~ Oleksii > > Jan > > > Release: July 17 > > The release date is shifted, but it still remains in July, which > > seems > > acceptable to me. > > > > One more thing: > > No release ack is needed before Rc1. Please commit bug fixes at > > will. > > > > Have a nice day. > > > > Best regards, > > Oleksii >
|
Lists.xenproject.org is hosted with RackSpace, monitoring our |