> Planned release schedule for Xen 4.16 (recap):
>
> Friday 24th September PASSED Last posting date
>
> Patches adding new features should be posted to the mailing list
> by this cate, although perhaps not in their final version.
> (3 weeks)
>
> Friday 15th October Feature freeze
>
> Patches adding new features should be committed by this date.
> Straightforward bugfixes may continue to be accepted by
> maintainers.
As previously noted, we have had a lack of review bandwidth which
means this release will be light on content. We discussed but
rejected the possibility of extending the release (beyond Christmas,
to some time in January/February).
Under the circumstances, and considering some external constraints, I
am considering trying to *compress* the release schedule by
approximately one week. The feature freeze data would remain the same
- we need to give people as much time to get things reviewed and into
tree as we can, but I think we can probably cut a week off the freeze.
That would look roughly like this:
> Friday 15th October Feature freeze
(2 weeks)
Friday 29th October **tentatve** Code freeze
Bugfixes only, all changes to be approved by the Release Manager,
on the basis of a (progressively stricter[*]) risk assessment.
(2 weeks)
Friday 12th November **tentative** Hard code freeze [*]
Bugfixes for serious bugs (including regressions), and low-risk
fixes only.
(0.5 weeks)
Tuesday 16th November **tentative** Branch off staging-4.16
xen-unstable open again - with caveats to avoid release disruption.
(1.5 weeks)
Friday 26th November **tentative** Final commits (docs/prep only)
Week of 29th November **tentative** Release
(probably Tuesday or Wednesday)