Subject: Status update
Ian,
We had another 14” of snow which screwed up this Monday and Tuesday Morning.
We could not install the remain servers.
DonK reported having problems with the repaired COMTROL.
I tested it today. It passed all the controller tests, bur failed the port test using the COMTROL supplied LOOP BACK plugs.
I spoke to Nick Thomas at Comtrol Tuesday and will report my results to him today.
We installed the Comtrol Components with kid gloves. We could not have been any more careful. I will investigate
with Nick later today. I understand that this is a critical piece of equipment and is on the critical path.
I am attaching the latest connection spread sheet.
The PDU’s and the Switches have Web Interfaces if you have a need to control them for now.