[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [Wg-test-framework] Test project costings -- EarthLink
I promised to send a worked-out costing for going with EarthLink (datacenter)
and
All-Net (Sys Admin & backup).
Things which need to be included:
Hosting in a proper datacentre[0]
Space charges[1]
Power charges
External internet connection (at least one
for each infrastructure server) [2]
Bandwidth charges [3]
Inter-rack connectivity if expand to multiple racks
Physical rack cabinet
PDU-controlled socket for each machine
Backups
Remote serial console access to infrastructure servers
Sysadmin on contract basis
Assumptions:
Space and power:
2 infrastructure servers at 2U and 200VA (~=200W) each
24 test servers at 1U and 200VA each
1 internal switch at 1U, 100VA
1 external switch at 1U, 100VA
For a total of 30U, 5400VA
Bandwidth:
Total external 2Mbit/s 95%ile.
Contract sysadmin from All-Net Computer Solutions
100h setup over one to two weeks.
4h per week ongoing (includes backup).
Things NOT included (to match Jump costings):
Servers, testbed systems
Internal switches
Internal CAT-45 wiring
Multi-port serial boards
Serial leads
All-Net does have a guess for the hardware at $53,079 (L30,993).
The proposal would involve the following invoice line items from EarthLink
(Note: Quote has expired (June 11, 2014) and so may change):
* Colo total rack power 4x 30A 208V 3 phase for ~4800VA per. So
expected that 2 will do. Cost is based on actual use with a base
add of $110/month
* EarthLink setup: $935
* Consultancy $85/hr, 100h setup, 4h ongoing: $8500 setup, $1360/month.
Bottom line:
Total $3034/month, $9435 setup. At the current exchange rate of
US$1 = UKL0.58392, that's L1772/month, L5509 setup.
Notes:
The power budget above is probably an overestimate, perhaps by a
factor of two or so, so the bottom line I have quoted is a maximum.
EarthLink's quote is for a 3-year term, they may be able offer us a "empty" 2
rack (I.E. if we expand soon, the 2 racks could be next to each other, otherwise
so sort of inter rack networking can be setup). If we don't have certainty of
funding for a 3-year term we can probably negotiate a shorter term with a higher
commitment.
I have attached a spreed sheet with all the numbers for both EarthLink and Jump.
And the All-net details.
-Don Slutz
[0] In this case EarthLink @ Marlborough (SSAE 16 SOC2)
http://www.earthlinkbusiness.com/cloud/data-center/colocation.xea
[1] Earthlink has a cost per rack.
[2] Earthlink actually offer 22 connections per rack.
[3] Earthlink bundle 2Mbit/s 95%ile per rack.
Attachment:
Wg-test-framework Document-1.pdf Attachment:
XenProjectColo.ods _______________________________________________ Wg-test-framework mailing list Wg-test-framework@xxxxxxxxxxxxxxxxxxxx http://lists.xenproject.org/cgi-bin/mailman/listinfo/wg-test-framework
|
![]() |
Lists.xenproject.org is hosted with RackSpace, monitoring our |